The winner of the pre-project works was determined in the construction of the airport in Zakarpattia
The winner of the tender for the implementation of pre-design works for the construction of the airport in Transcarpathia was the consortium "Land Bud Project UA". The expected cost of the works will be UAH 4,220,000. with reference to the CTS.
A total of 7 companies took part in the auction. The cost of work during the auction decreased from 5 million to 4 million 220 thousand UAH. The task of pre-design works is to determine the location of the new airport in Transcarpathia. Currently, two locations for its construction are being considered - Seredne and Mukachevo.
Pre-design works will last about 3 months. After determining the final location of the runway, the development of design documentation will begin. The construction of the airfield in Transcarpathia will take approximately three years.